alert arrow-rightCreated with Sketch. calendar check clock delete downloadCreated with Sketch. facebook-sq facebook flickr google-plus home info instagram linkedin-sq linkedin list location mail minus nav-down nav-left nav-right--narrow nav-right nav-up pinterest plus related-documentsCreated with Sketch. rows rss search settings tumblr twitter vimeo vine wordpress youtube

Eagle Stadium, Allen ISD

Location

Allen, Texas

Size

70,000 sq. ft.

Datum Engineers and Nelson Forensics worked together for nearly two-years on this joint effort of evaluation and rehabilitation of the Eagle Stadium in Allen, Texas. The $60M facility is touted as the most expensive high school stadium in the United States.

The Datum Nelson team of 15 engineers analyzed Eagle stadium's as-built condition, diagnosed structural deficiencies, designed structural repairs for multiple elements of the stadium, and provided oversight during the construction process.

The engineers' efforts focused primarily on the following elements of the stadium:

  • Concession stands
  • Entry towers and access gate ramps
  • Press box
  • Scoreboard
  • Basement walls
  • Concourse level slab, beams, and girders